Millions lost due to Kompanna Veediya flyover construction delay

Published

on

Minister of Transport, Highways, Ports and Civil Aviation – Bimal Rathnayake yesterday (April 28) visited construction site of the flyover being built from Baladaksha Mawatha near the Kompanna Veediya Police Station to Chittampalam A. Gardiner Mawatha, in Colombo, to inquire about the cause of its delay.

He pointed out that the government has been compelled to pay over Rs.400 million to contractors as delay charges and a significant daily loss of Rs. 500,000 is being incurred.

The flyover has been planned to be built from Baladaksha Mawatha near the Slave Island Police Station to Chittampalam A. Gardiner Mawatha, in Colombo.

Accordingly, 06 police residential quarters had to be removed, and as a result, the project was delayed for about 02 years.

According to the Transport Ministry, it was informed during the inspection tour that steps will be taken to promptly remove the police residential quarters, which have caused the delay.

Stating that the matter must be resolved immediately, the minister has instructed the relevant officials to ensure that the construction of the flyover is completed by the end of this year under any circumstances.