Connect with us

News

“No investments coming in under new capital-based package”

Published

on

The Ministerial Consultative Committee on investment Promotion advised the Board of Investment of Sri Lanka (BOI) to clearly communicate to the Central Bank of Sri Lanka (CBSL) and the Treasury that there are no investments coming in under the new enhance capital-based package and therefore a new package should be introduced.

This issue was addressed at the first meeting of the Ministerial Consultative Committee on Investment Promotion held recently (15), chaired by State Minister of Investment Promotion – Dilum Amunugama.

Addressing the aforesaid issue, Member of Parliament – Dhammika Perera emphasized the importance of clearly communicating the aforesaid to the CBSL and the Treasury as they need to have a clear understanding on the matter when carrying out negotiations with the IMF.

Accordingly, the Committee instructed the BOI to present data on how many projects have been received under the enhance capital-based package and how much employment and investment have been brought in under the new package at its next meeting.

Responding to the said concern, BOI officials present stated that there is no concession that they can offer as the BOI in par with the other countries, because all the tax holidays were removed and therefore a decline can be observed in the investors coming in.

Furthermore, the possibility of amending the law to enable foreigners to purchase land was also discussed.

State Ministers Diana Gamage, Prasanna Ranaweera, A. Aravindh Kuma as well as MPs Milan Jayathilake, Janaka Wakkumbura and Gunathilaka Rajapaksha were present at the Committee meeting held.

News

BASL Bar Council condemns Tiran Alles’ statement, calls for resignation

Published

on

By

The Bar Council of the Bar Association of Sri Lanka (BASL) yesterday passed a resolution condemning the recent statement made by Public Security Minister Tiran Alles calling upon newly-passed out police recruits that it was not a sin to eradicate criminals.

BASL President Kaushalya Nawaratne told the Sunday Times that the resolution was moved over the statement made by the Minister on Thursday at the passing out parade of specially-trained officers of the first combat motorbike unit to eradicate criminal elements in the Western and Southern Provinces at the STF Camp in Katukurunda, Kalutara.

The Minister told the officers “it is not a sin” to eradicate those involved in murders, selling drugs and trafficking drugs.

The Bar Council resolved that if the Minister does not step down, the President should take action to remove him from the Public Security Ministry post, Mr Nawaratne said.

The Bar Association stated that they would resort to local as well as international legal action if the Minister would not be removed from his position.

Mr Nawaratne said that the statement comes in the wake of a breakdown of the law and order situation and alleged that the Sri Lanka Police was involved in various illegal acts in the recent months.

(sundaytimes.lk)

(Except for the headline, this story, originally published by sundaytimes.lk has not been edited by SLM staff)

Continue Reading

News

Sri Lanka faces challenges in mega project implementation

Published

on

By

More than 300 contracts connected to 35 mega projects were suspended last year, and Rs. 2.3 billion was demanded as compensation by contractors for just nine of them, the Finance Ministry’s Project Management and Monitoring Department (PMMD) says, adding there is a probability that claims will also be submitted over another 22.

A total of 37 projects achieved no physical progress during the last quarter of 2023, according to the PMMD’s latest report released last month.

Among them are 17 projects out of 33 for which foreign disbursements were stopped.  Implementation delays are reported in 41 other projects owing to the poor performance of contractors. As this issue prevails in about 20 percent of total projects, it is important to consider the performance of contractors as a criterion for the renewal of their registration to resolve the repetition of this issue, the report states.

The PMMD’s latest data come amidst strong words in the International Monetary Fund’s (IMF) Governance Diagnostic Assessment, which pointed to recurrent problems in how successive Sri Lankan governments carried out mega projects.

Citing the PMMD’s 2022 fourth-quarter report, the multilateral lender notes that the most common issue affecting implementation is the delay in receiving allocation and imprest, “which proves that projects have commenced without appropriate budgetary allocations in the annual budget.” Another was the delay in land acquisition, it states, “again showing that projects are initiated without actually being ready”.

There are also procurement-related matters, the absence of performance indicators and outputs and the poor performance of contracts. And the Ministry of Finance “lacks basic information on projects, including the expected revenues and the potential cost of early termination given the limited data provided on projects and problems accessing necessary data”.

The PMMD’s new report says that delays have been a common practice, with “no evidence reported on actions taken against the responsible parties who have not taken appropriate steps for time management in projects, resulting in the failure of economic plans formulated based on the expected benefits of projects”.

The time period agreed upon for delivering outputs in an astounding 99 projects had lapsed at the end of last year while 20 of them obtained extensions beyond four years. Thirteen projects have not met even 25 percent of the expected target, even after more than half the project period, the PMMD notes.

For the first time, the PMMD has identified 30 projects that faced major implementation delays, including the Irrigation Ministry’s Uma Oya Multipurpose Development Project, which was inaugurated this week after ten extensions.

Another flagged project is the Irrigation Ministry’s Asian Development Bank-funded Mahaweli Water Security Investment Programme, the scope of which was drastically reduced by withdrawing 11 out of 21 packages owing to failure to execute them within the planned timeframe as well as the inability to begin new contracts in a restricted financial situation.

“The most complex tunnel construction package, which is currently ongoing and achieved about 20% progress, should be completed within 18 months and the balance loan amount of USD 159 million should be disbursed during this period Otherwise, that loan amount will be cancelled without any use.” the PMMD warns.

(sundaytimes.lk)

(Except for the headline, this story, originally published by sundaytimes.lk has not been edited by SLM staff)

Continue Reading

News

“230 rehab centers island-wide tackle drug addiction”

Published

on

By

The National Dangerous Drugs Control Board says that 230 rehabilitation centers have been established to treat drug addicts in the country.

Its Chairman Attorney Shakya Nanayakkara says that the services of these rehabilitation centers will commence from the 7th of May.

The centers can accomodate up to 20,000 patients.